Sprint Planning Overview

Sprint Capacity

30 Story Points

3 devs × 10 SP each

Total Estimated Work

57 Story Points

2 Sprints (4 weeks)

Team Velocity

3 Backend Developers

Parallel development

Parallel Development Strategy

With 3 backend developers, we can work on different domains simultaneously to maximize throughput.

Developer A

Focus: Equipment Management & Core Foundation

Sprint 1: Database Setup + Equipment APIs (15 SP)

Sprint 2: Equipment Features + Testing (15 SP)

Database Setup Equipment Management

Developer B

Focus: Request Management & Inspections

Sprint 1: Request Management APIs (15 SP)

Sprint 2: Inspection System + Integration (15 SP)

Request Management Inspections

Developer C

Focus: Financial & Timesheet Systems

Sprint 1: Payment Management APIs (11 SP)

Sprint 2: Timesheet System + Integration Testing (6 SP)

Financial Management Timesheet Management

Sprint 1 (Weeks 1-2)

  • Dev A: Database setup + Equipment CRUD
  • Dev B: Request management system
  • Dev C: Payment tracking + cost calculations
  • Total: 30 SP

Sprint 2 (Weeks 3-4)

  • Dev A: Equipment features + optimization
  • Dev B: Inspection system + workflows
  • Dev C: Timesheet system + integration testing
  • Total: 30 SP

Backlog Summary

Equipment Management

6 Stories 18 SP

Request Management

5 Stories 15 SP

Inspections & Checklists

4 Stories 12 SP

Financial & Payments

2 Stories 5 SP

Timesheet Management

2 Stories 6 SP

Implementation Epics & User Stories

Epic 1: Database Setup & Entities

Sprint 1 3 SP 2 Stories Dev Team A

Create logistics-specific database tables and JPA entities (ERP infrastructure already exists).

DB-001 2 SP Critical Dev A

As a developer, I need to create logistics-specific database tables

Create equipment, requests, inspections, and financial tables in existing ERP database.

Acceptance Criteria:
  • 23 logistics tables added to ERP database schema
  • Foreign keys linked to existing ERP tables (users, projects, etc.)
  • Indexes and sequences created
  • Migration scripts prepared
Tasks:
  • Create equipment & request tables (1 day)
  • Create inspection & financial tables (0.5 days)
  • Add constraints and test data (0.5 days)
ENT-001 1 SP Critical Dev A

As a developer, I need to create JPA entities for logistics domain

Create JPA entities using existing ERP base classes and annotations.

Acceptance Criteria:
  • All logistics entities extend ERP BaseEntity
  • Relationships mapped to existing ERP entities
  • Validation annotations applied
  • Entities tested with ERP's DataSource
Tasks:
  • Create entities using ERP patterns (1 day)

Epic 2: Equipment Management API

Sprint 1-2 18 SP 6 Stories Developer A

Epic 3: Request Management API

Sprint 1-2 15 SP 5 Stories Developer B

Epic 4: Inspections & Checklists API

Sprint 2 12 SP 4 Stories Developer B

Epic 5: Financial & Payments API

Sprint 1 5 SP 2 Stories Developer C

Epic 6: Timesheet Management API

Sprint 2 6 SP 2 Stories Developer C